Why most projects fail before they start

The problems that sink a project are usually visible in its first two weeks. Here is what to look for, and what to do about it.

When a project goes wrong, the story people tell is about the end: the deadline slipped, the budget ran out, the result wasn’t what anyone wanted. I think the story usually starts much earlier. The troubled projects I’ve looked at were mostly in trouble within their first two weeks, and nobody said so at the time.

I find that encouraging. A cause that shows up in week one can be dealt with in week one, when changing course costs a conversation and not a rebuild.

To keep this concrete I’ll use one made-up project all the way through. Imagine a twelve-person accountancy firm that wants a new website. The budget is £15,000 and the partners want it live in ten weeks. Nothing about it is unusual, which is the point.

Five people, five projects

The first thing I do on any piece of work is ask the people involved, separately, what success means. On the imaginary website I’d expect answers like these. The senior partner wants the firm to look more established. The partner who handles new business wants more enquiries. The office manager wants to stop answering the phone to people asking about fees. The junior who updates the current site wants to be able to change a page without calling an agency. The designer wants something for the portfolio.

Each of those is reasonable, and they pull in different directions. A site built to look established is a different site from one built to cut phone calls. If nobody chooses, the team will try to serve all five and the £15,000 will be spread too thinly to do any of them well.

So before work starts I ask the sponsor to finish one sentence: “This project will be a success if, by a certain date, the following is true.” For the accountancy firm it might come out as: “By the end of March, a visitor can see our fees and book a first call in under two minutes from any page.” You can test that. You can also disagree with it, and I want people to. An argument about that sentence in week one takes an afternoon. The same argument in week eight means throwing away finished pages.

If the sponsor can’t write the sentence, I don’t treat it as a delay. Working it out is the first job, and it’s usually the hardest one on the whole project.

The list nobody sorts

Every project starts with more ideas than time. The accountancy firm will want the booking page, a fees page, staff profiles, a blog, a client login area, a tax calculator, and a chat window in the corner. All of that goes into a document, the document gets called the scope, and nobody notices that it has no order.

An unordered list works untill time gets tight, which on a ten-week project tends to be around week six. Then something has to go, and with no agreed order the choice goes to whoever objects most firmly in the meeting.

I sort the list into three groups with the sponsor in the room: what the project must deliver, what it should deliver if things go well, and what can wait for a later phase. For the website, booking and fees are in the first group because they’re the success sentence. Staff profiles and the blog are in the second. The client login and the calculator wait. Then I ask for that order to be confirmed in writing, even if it’s only a reply to an email. It takes about an hour and its rarely a comfortable hour, because it’s the first time someone hears that their idea is in the third group.

That raises the question of who the sponsor is. I want one named person who can decide. “The partners” isn’t a person. When the designer asks on a Thursday afternoon whether fees should be shown as fixed prices or as “from” prices, someone has to answer that day and the answer has to hold on Monday. With three sponsors, the question waits for the next partners’ meeting, and the meeting after that reopens it. If I join a project and find a committee at the top, getting it down to one name is what I work on first, ahead of the plan.

Slack, written down

I used to add a little padding to every task and say nothing about it. I’ve stopped. Hidden padding gets found sooner or later, usually when a task finishes early, and from then on the sponsor discounts every number you give them.

Now I put slack in the plan as its own line. On the ten-week website I would plan eight weeks of work and show two weeks labelled as contingency. Some sponsors push back and ask why the site can’t simply launch in eight. My answer is that the eight-week version only works if nobody is ill, the photographer turns up on the day, and the partners approve the copy first time. I wouldn’t bet on that, and the plan shouldn’t either.

The same goes for risks. The thing that goes wrong on a project is very often something a team member already suspected. On our website, the junior probably knows the partners take three weeks to approve any piece of writing. The designer may doubt that the booking tool will connect to the firm’s calendar. Neither says so, because there’s no obvious place to say it.

I keep a shared page with three columns: what might go wrong, how likely it is, and what we will do if it happens. For the slow approvals, the entry could read “copy sign-off takes longer than a week; likely; one partner signs off alone, the others see it after launch”. I care less about the page than about having a place where a doubt can be raised without it sounding like a complaint.

What I ask in week one

Before a project moves from talking to doing, I want answers to six questions:

  1. What will be true when this is finished?
  2. Who is the single person who decides?
  3. What is in scope, in order of importance?
  4. What is explicitly out of scope?
  5. Where is the slack in the plan?
  6. What are the three things most likely to go wrong?

None of this needs special software or a qualification in project management. It needs an hour or two of frank conversation before the work begins. If you are about to start something and can’t answer all six yet, answer them before you do anything else.